332:494:01/599:02 — final project 1 solved

$35.00

Category: You will receive a download link of the .ZIP file upon Payment

Description

5/5 - (1 vote)

The project should be simulation-based. It offers an opportunity to focus on a specific
subject or technology that are of interest. The course project includes running a system
simulation accompanied by a written report.
1. The project may be done individually or in teams of two students.
2. Project may be selected from the provided list or proposed by the students. A
minimum of 7 bus system needs to be selected by a team of two and a minimum
of 5 bus system for individual projects.
3. All material should be submitted electronically by uploading it into the
assignment folder or under the personal Sakai Dropbox.
4. Students may propose their own ideas for this project.
5. All code files should be uploaded in addition to the report.
Written report guidelines:
Use the IEEE conference paper template for the report writeup:
https://www.ieee.org/conferences/publishing/templates.html
The report needs to be at a minimum 3 pages long and maximum 6 pages.
The report should include the following analysis and information:
1. Title of the report and student(s) name(s) and RUID(s).
2. Introduction: a brief overview of the role of power flow analysis and its use for
contingency analysis or other applications.
3. Case study/Problem formulation: This section is where details of the related work are
explained. This section can include multiple subsections based on the topic discussed.
Problem formulation, model development, objectives, etc. For the selected system,
detail the admittance matrix, given powers and voltages and the method used to solve
it:
a) Use Gauss-Seidal (GS) method to find a good initial solution
b) Implement Newton-Raphson (NR) method, using the solution from the GS as
an initial guess.
332:494:01/599:02 — final project 2
c) Find all powers (real and reactive) flowing through the lines, the node
voltages and the line currents.
d) Choose one bus for contingency analysis. Assuming this bus is failing and
taken out of use, repeat the analysis for the new topology: find all powers (real
and reactive) flowing through the remaining lines, the node voltages and the
line currents under the new topology.
4. Detailed solution & discussion: mathematical representation of the solution and
power flow diagram, where relevant. Discussion on the simulation results: what are
the conditions for the line currents ampacity in order for the system to operate given
the assumed failure?
5. Conclusions: A brief discussion of the case analyzed, and the results obtained.
Include insight into your specific problem.
6. Appendix: detailed code
List of suggested projects:
For ONE of the following projects develop an appropriate on-line diagram. Write a
report and a general Matlab M-code or PowerWorld Model.
For ANY of these projects perform the following:
1) Compute the pu one-line model.
2) Compute all bus voltages using Gauss–Seidel method on Matlab
3) Use The GS solution as an initial solution, and compute all bus voltages using
Newtown–Raphson method on Matlab
3) Compute all power values including power flow on each line (in/out), line losses and
generated power. Compute all node voltages and line currents.
4) Contingency analysis: assume one of the busses has a fault thus we need to simulate
the same system without this line. How does it change the power flow over the lines?
Compute all power values including power flow on each line (in/out), line losses and
generated power. Is there any significant change in one (or more) of the lines?
Project Option 2.1
The one-line diagram of a power grid is depicted in figure 1. The details for the grid are
given in the figure. Assume a base power of 100MVA and base voltage of 13.2 kV.
Assume the input reactance of the local power grid is 10% based on the transformer T1.
The input resistance of the PV sources is 7% based on their rating and input reactance of
other sources is 7% base on their ratings.
The system data:
Transformer T1: 20 MVA, 33 /13.2 kV, 10% reactance
Transformer T2: 20 MVA, 13.2 / 3.3 kV, 12% reactance
Transformer T3: 5 MVA, 3.3 / 460 V, 6.5% reactance
Transformer T4, T5, and T6: 2 MVA, 3.3 / 460 V, 6.5% reactance
332:494:01/599:02 — final project 3
Transformer T7: 5 MVA, 3.3 / 460 V, 6% reactance
Transmission line impedance is given in Table 2
Table 2: Transmission Line Data for project 2.1
Line Resistance (Ω) Series Reactance (Ω)
8–9 .05 0.5
9–10 0.04 0.4
9–11 0.04 0.51
11–12 0.04 0.5
11–13 0.01 0.12
13–14 0.03 0.32
14–15 0.04 0.45
The local loads (bus 16, bus 17 and bus 18) and bus 8 are set at 1 MVA at 0.85 power
factor lagging.
332:494:01/599:02 — final project 4
Figure 1: System for projects 2.1
Project Option 2.2
CB CB
CB
CB
CB CB CB
CB
CB
CB
CB
CB CB CB
1.2 MW
0.62 MVar
11
7
To Feeder
1
HV Bus Infinite
Bus
Local
Utility
Utility EMS
Net
Metering
8
9
10
12
0.05 +j0.5
0.04 +j0.51
0.04 +j0.4
0.01 +j0.12
0.04 +j0.5
A Zone with DGs
(Micro-Grid System)
1.18 MW
0.62 Mvar
DG
EMS
0.03 +j0.32
CB CB
CB
CB
CB
CB
0.04 +j0.45 CB
CB
16 17 Local
Loads
18
0.9 MW
0.48 Mvar
15
1.06 MW
0.56 Mvar
Gas turbine
Sync. Gen.
1.8 MVA
14
13
2
3
CB
CB CB
CB CB
CB
CB
Local
Loads
Local
Loads
Variable Speed
Wind Turbine with
DFIG (2 MW)
CB CB
T1
13.2 / 3.3 kV
20 MVA
Xt = 12%
4.5 MW
2.2 MVar
0.99 MW
0.54 MVar
0.96 MW
0.51 MVar
0.9 MW
0.48 MVar
CB CB
G
G
DC/AC
PV
Station
DC/AC
PV
Station
DC/AC
PV
Station
1 MW 1 MW 1 MW
4 5 6
T2
T3
T4 T5 T6
T7
332:494:01/599:02 — final project 5
Figure 2: System for projects 2.2
PV generating station #1: 2MVA; internal impedance 50%
Gas turbine: 1MVA; internal impedance 4%
Transformers: 460V/13.2kV (Y/D) ; 10% internal reactance; 10MVA rated power (all
three phase)
Power grid transformer: 20MVA; 63kV/13.2KV; 7% reactance
B4 load: 1.5MW; pf=0.85 lag
B5 load: 5.5MW; pf=0.9 lag;
B6 load: 4MW; pf=0.95 lag;
B7 load: 5MW; pf=0.95 lag;
B8 load: 1MW; pf=0.9 lag;
Transmission Line Data for project 2.2
332:494:01/599:02 — final project 6
Resistance: 0.0685 ohm/mile; reactance: 0.4 ohm/mile; half line charging admittance:
11×10-6 siemens/mile
Line 4-7: 5 miles
Line 4-8: 1 miles
Line 5-6: 3 miles
Line 5-7: 2 miles
Line 6-7: 2 miles
Line 6-8: 4 miles
Project Option 2.3
For the single-line diagram in Figure 4 convert all positive-sequence impedance, load,
and voltage data to per unit using the given system base quantities.
Run the power flow program and obtain the bus, line, and transformer input/output
voltages
Figure 4 (a): System for project 2.3
332:494:01/599:02 — final project 7
Figure 4: System for project 2.3
Project Option 2.4
For the single-line diagram in Figure 5 convert all positive-sequence impedance, load,
and voltage data to per unit using the given system base quantities.
Run the power flow program and obtain the bus, line, and transformer input/output
voltages
(Comment: for L2 please choose a value between 20km to 50 km)
332:494:01/599:02 — final project 8
Figure 5: System for project 2.4
Project Option 2.5
Propose/choose a power network example with at least 7 buses (either an IEEE test bus,
or other examples from the course textbooks). Provide the system details (i.e. generating
sources, transformers, loads, etc.). Develop the per unit model for the systems. Run the
power flow program and obtain the bus, line, and transformer input/output voltages
(Comment: for L2 please choose a value between 1km to 5km)